Financial Approvals - September
September 18, 2023 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Merton Cabinet approved financial adjustments and transfers on 18/09/2023. Cabinet approved adjustments to the Capital Programme, treated the School Capital Maintenance Budget as one for financial management, approved transfers from CLLF reserves to Early Years programmes, and approved the transfer of 'Your Merton' balance to the Environment, Civic Pride and Climate department.
Full council record
Purpose
That Cabinet approve any financial adjustments and/or transfers as required
Decision
RESOLVED :
A. That Cabinet approved the adjustments to the Capital Programme in the Table below:
Budget
2023-24
Budget
2024-25
Budget
2025-26
Budget
2026-27
Narrative
£
£
£
£
Finance & Digital
Clarion CPO
(12,088,650)
1,212,820
1,230,000
Re-profiled in accordance with projected spend £5.8m to 27-28
Children, Lifelong Learning & Families
West Wimbledon- Capital Maintenance
35,960
Virement from the Unallocated Maintenance Budget
Dundonald - Capital Maintenance
7,720
Virement from the Unallocated Maintenance Budget
Pelham - Capital Maintenance
(8,190)
Virement to the Unallocated Maintenance Budget
Liberty - Immersive Learning Centre
(11,710)
Scheme complete Budget Release back to NCIL
Lonesome - Capital Maintenance
(8,440)
Virement to the Unallocated Maintenance Budget
William Morris - Capital Maintenance
47,360
Virement from the Unallocated Maintenance Budget
Unallocated Primary School - Capital Maintenance
(168,410)
Net Budget Adjustments after Virements
Perseid Lower - Capital Maintenance
94,000
Virement from the Unallocated Maintenance Budget
Environment, Civic Pride & Climate
On Street Parking - P&D - ANPR Cameras
(150,000)
150,000
Reprofiled in accordance with projected spend
Highways & Footways - Pollards Hill Cy & Active Travel
(200,000)
200,000
This was programmed for Q4 23/24. Walking and Cycling Strategy will complete in Jan: Capital projects to follow on afterwards but expected to be in 2024/25
Parks Investment - Martin Way - Greener, Brighter & Revitalised
93,840
£60k vired from Civic Pride to top up NCIL budget of £23,840
Parks Investment – Abbey Rec
(7,470)
NCIL Budget Transferred to Revenue
Housing & Sustainable Development
Mitcham Area Regeneration - Pollards Hill Bus Shelter
(300,000)
300,000
Civic Pride Reserves (revenue) allocated to create staff resource to run the project. Capital spend will be later once project has re-established. Re-profile capital (CIL) spend to 2024/25 onwards
Morden Area Regeneration - Crown Creative Knowledge Exchange
80,000
Vired for shop front element of scheme
Borough Regeneration - Shop Front Improvements
(60,000)
(80,000)
Budget reprofiled and vired to Morden Lnowledge Exch.
Total
(12,643,990)
1,782,820
0
1,230,000
B. That the School Capital Maintenance Budget is treated as one budget for financial management, reducing substantially the level of formal approval required for budget virement sign off to provide valuable historic information whilst allowing for effective budget management. This item will also be reported to Council
C. That Cabinet approved transfers from CLLF reserves:
£240,000 to Early Years - ringfenced funding for transforming families’ programme.
£247,861 to Early Years - ringfenced funding for transformation hubs.
D. That Cabinet approved the transfer of £162,796.37 of the ‘Your Merton’ balance currently held in the ‘Civic Pride’ reserve fund, to be spent by Environment, Civic Pride and Climate department in 2023/24.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 18 Sep 2023 |
| Effective from | 26 Sep 2023 |
| Subject to call-in | Yes |