Affordable Housing Programme First 93 Units across 4 Sites
October 14, 2024 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve the total project expenditure for delivering the first 93 social rent homes across four sites, recommend that Full Council approve a £27.87m increase to the capital programme, note the upcoming procurement process, and delegate contract approval authority to specified officers.
Full council record
Purpose
Pursuant to the Collaboration Agreement
entered into in November 2023 this paper will request approval to
the total project expenditure including on costs for the delivery
of the first 93 Social Rent homes across 4 sites in the Council's
sustainable homes programme.
Decision
RESOLVED:
That Cabinet:
A.
Noted the progress on the programme for the delivery of 93 new
affordable homes.
B.
Noted the contents of Section 4 of the report with the financial
detail set out in Exempt Appendix A) summarising the financial
impact of the revised scheme and recommend that Full Council
approves the increase to the capital programme and its funding
totaling £27.87m.
This adjustment to
the approved capital programme will also be included in the
financial monitoring report elsewhere on this Cabinet’s
agenda.
C.
Noted that the procurement process for the construction packages is
being prepared and tenders will be issued and returned for
different packages from early in 2025.
D.
Delegated authority to the Executive Director for Housing and
Sustainable Development, in consultation with the Cabinet Member
for Housing and Sustainability, the Cabinet Member for Finance and
Corporate Services and the Executive Director of Finance and
Digital, for final approval of the contracts following the outcome
of the tendering process.
E.
Noted the longer-term officer resource implications identified in
paragraph 4
Related Meeting
Cabinet - Monday 14 October 2024 7.15 pm on October 14, 2024
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 14 Oct 2024 |
| Subject to call-in | Yes |