Ringwood Depot Accommodation Refurbishment Project

March 2, 2026 Strategic Director of Corporate Resources and S151 Officer (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to pause the delivery of the Portakabin welfare accommodation works until a full planning application is approved, acknowledging the associated financial implications of this temporary stop-work instruction.

Full council record

Purpose

Following a review of site plans by Hampshire
County Council (HCC), concerns were raised regarding the
applicability of Part 12, Schedule 2 of the General Permitted
Development Order (GPDO) 2015.

A full application will be prepared and referred to April Planning
Committee

Due to the need for planning permission, and to ensure the project
proceeds on a fully compliant basis, the works should pause until
the appropriate approval route is in place.

Decision

To pause delivery of the Portakabin welfare
accommodation works pending the outcome of a full planning
application, following receipt of corrected planning advice
confirming that the proposed linked Portakabin welfare building
does not benefit from permitted development rights and therefore
requires express planning permission.

This pause includes agreement to the associated financial
implications arising from issuing a temporary stop works
instruction to the contractor.

Supporting Documents

Ringwood Depot - Planning - 2 March 2026.pdf

Details

OutcomeRecommendations Approved
Decision date2 Mar 2026