BEC Solar PV project management

June 19, 2026 Head of Environmental Enhancement (Officer) Approved View on council website
Full council record

Decision

To waive the request for waiver and award the contract to Clough Management in relation to providing project management services for the proposed PV solar array at Brynsworthy Environmental Centre

Reasons for the decision

To provide project management services for the proposed PV solar array at Brynsworthy Environmental Centre
• Developing a programme and maintaining the programme monthly
• An initial meeting on site to better understand the project scope
• Monthly team meetings via TEAMS and minutes
• Developing an initial risk register/
• Early Warning Register and updating it monthly
• Overviewing the preparation of the tender documents Reviewing the quality aspect of tender returns
• Acting as Contract Administrator or NEC Project Manager
• Issuing monthly payment Certificates and Certificate of Practical Completion
• Attending a monthly contractor progress meeting on site in person.
• Chairing the meeting and issuing minutes.
• Maintaining a schedule of defects, post completion
• A final site inspection
• Issuing the final payment Certificate

Alternative options considered

The contractor providing quote 3 was asked if there was a particular reason why the quote was low and provided an email response. The response was not considered to be definitive enough to warrant accepting the lowest quote.

Quotation 1:
Does the quotation conform to the provided specification? Y

Supplier Name: Clough Management
Quotation Price: £20,262

Quotation 2:
Does the quotation conform to the provided specification? Y

Supplier Name: WT Hills
Quotation Price: £21,000

Quotation 3:
Does the quotation conform to the provided specification? Y

Supplier Name: Expedite
Quotation Price: £10,000

Supporting Documents

BEC Solar PV project management.pdf

Details

OutcomeRecommendations Approved
Decision date19 Jun 2026