RESOLVED -
 

(1)           
That Cabinet noted the progress on the project to
regenerate the Prefabricated Bungalows at Stonebroom, including the option to consider
delivery of a new community building to replace existing
provision.  
 

(2)           
That Cabinet approved demolition notices be issued
to 40 tenancies of the bungalows.
 

(3)           
That Cabinet approved RHL’s request to award
Band 1 priority housing application status to seven tenancies of
the bungalows, who have expressed an interest in relocating away
from the project.
 

(4)           
That Cabinet approved further detailed design,
engineering and construction planning works be undertaken for the
project with a budget cost of £0.5m (from within the approved
budget) in advance of the main construction contract.
 

(5)           
That Cabinet noted temporary decants of existing
customers will be required into current voids on the development.
This is necessary to facilitate the construction programme and
ensure the scheme is viable.
 

(6)           
That Cabinet noted existing gardens, access paths
and open grass spaces will need to be incorporated into the
construction area in a flexible manner, to provide sufficient
storage, access and working space for the construction team during
redevelopment.
 
REASONS FOR DECISION - The regeneration
scheme at Stonebroom supports the
Council’s commitment in its Council Plan to build, acquire
and facilitate the delivery of more high-quality social housing for
rent in the District. 
 
OTHER OPTIONS CONSIDERED AND REJECTED -
Not applicable.
 
Please note
that this was not a Key Decision and so can be implemented with
immediate effect by officers.

Supporting Documents

Appendix 1 - Site Plans.pdf
Stonebroom Development Update.pdf
Appendix 2 - Location of Voids.pdf

Details

OutcomeRecommendations Approved
Decision date28 Mar 2024