Leases for the Fakenham Leisure and Sports Hub Project

January 19, 2026 Approved View on council website
Full council record

Decision

Decision
RESOLVED to
 
·              
Grant a ’99 years less one day’ lease to UKPN for the
construction and operation of a substation on Trap Lane land.
 
·              
Delegate approval to the Asset Strategy Manger or the Assistant
Director for Finance and Assets to agree the exact terms of the
above legal agreement.
 
Reason for the decision:
 
The substation is essential for the leisure
centre expansion project. Without this lease, the new substation
cannot be built which would mean the power demands of the new
facility could not be met.
 

Related Meeting

Cabinet - Monday, 19th January, 2026 10.00 am on January 19, 2026

Supporting Documents

Cabinet Report FLASH UKPN Lease FINAL.pdf

Details

OutcomeRecommendations Approved
Decision date19 Jan 2026