Tin Footbridge, Skipton - Span 2 Replacement - Future Award of Contract
September 3, 2024 Assistant Director - Resources (Environment) (Officer) Key decision Approved View on council websiteFull council record
Purpose
To seek to award the tender for the Tin
Footbridge Span 2 replacement.
[The budget for the scheme is £450k, however, it is
recognised that the tender returns may exceed £500k due to
the current unpredictability in tender prices, particularly with
design and build contracts. Therefore a Key Decision may be
required.]
Decision
To tender the scheme for the replacement of
Tin Footbridge (Span 2) Design and Build contract.
Details
| Outcome | Recommendations Approved |
| Decision date | 3 Sep 2024 |
| Subject to call-in | Yes |