Cambois Quay - Dock Operator Appointment

October 6, 2026 Cabinet (Cabinet collective) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Cabinet of Northumberland Council decided on 06/10/2026 to approve the award of a revenue grant of up to £3.744 million to Advance Northumberland (Commercial) Limited. This decision approves an initial allocation of up to £1.301 million from the Strategic Management Reserve, with the remainder to be met from future business rate retention income. Authority is delegated to the Executive Director of Transformation and Resources and the Executive Director of Place and Regeneration to approve the Full Business Case, final grant award, and enter into the grant funding agreement.

Full council record

Purpose

To seek cabinet approval to provide grant funding support to Advance Northumberland (Commercial) Ltd to bring the Cambois Quay into full operational use through the appointment of a dock operator.

Decision

RESOLVED that Cabinet:-

(a)     approve the award of a revenue grant of up to £3.744 million to Advance Northumberland (Commercial) Limited for the period from 1st  May 2026 to 31st  March 2036, to support eligible contributions towards the Cambois Quay Dock Base Facility Charge;

(b)     approve an initial allocation of up to £1.301 million from the Strategic Management Reserve and agree that, once this allocation has been fully applied, the remaining contribution of up to £2.443 million is to be met from future business rate retention income generated through the Blyth Energy Central Investment Zone Site;

(c)      delegate authority to the Executive Director of Transformation and Resources (Section 151 Officer), in consultation with the Executive Director of Place and Regeneration, to approve the Full Business Case and final grant award, subject to satisfactory independent appraisal, confirmation of affordability and funding availability, completion of all required due diligence, and a compliant subsidy control position;

(d)     delegate authority to the Executive Director of Place and Regeneration, in consultation with the Executive Director of Transformation and Resources (Section 151 Officer), to agree the final terms and enter into the grant funding agreement and any ancillary documentation;

(e)     require the grant funding agreement to include appropriate provisions covering eligible expenditure, evidence of defrayal, annual review, performance and financial monitoring, recovery of overpayments, clawback, subsidy control compliance, audit, suspension and termination, and to provide that the Council's annual and total contribution does not exceed the approved caps;

(f)      delegate authority to the Executive Director of Place and Regeneration, in consultation with the Executive Director of Transformation and Resources (Section 151 Officer), to approve non-material amendments during delivery, provided that these do not increase the Council's maximum financial commitment or materially alter the purpose of the grant; and

(g)       require a formal mid-programme review to be undertaken by the Executive Director of Place and Regeneration, in consultation with the Executive Director of Transformation and Resources (Section 151 Officer), to assess continuing need, value for money, progress towards a commercially sustainable multi-user operating model and the appropriateness of continued grant support.

Related Meeting

Cabinet - Tuesday, 6th October, 2026 10.00 am on October 6, 2026

Supporting Documents

Cambois Quay - Dock Operator Appointment.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date6 Oct 2026
Effective from12 Oct 2026
Expected date6 Oct 2026
Originally due8 Sep 2026
Lead officerMaria Antoniou, Alex Black, Sarah McMillan, John Hildreth
Subject to call-inYes