Post-fire reinstatement works to a Council property

October 21, 2026 Approved View on council website
Full council record

Decision

Cabinet resolved to:

  1. Approve the project to build a pair of semi-detached dwellings at 26 Stubbs Avenue, Oxford OX3 8RT, as detailed in this report, and include the scheme within the Affordable Housing Supply Programme, noting the delivery of one additional new-build home and the replacement of one home lost following a major fire.
  2. Approve an in-year budget virement of £854,700 within the HRA Capital Programme, transferring funding from the "New Pipeline" allocation within the "OCHL Purchases" budget line to a dedicated budget line for this scheme.
  3. Delegate authority to the Director of Housing to take all actions and make all decisions necessary to facilitate and deliver the project, including undertaking the necessary procurement processes and entering into all agreements necessary to deliver this project following consultation with the Director of Group Finance, Director of Law & Governance and the Lead Cabinet Member, except where there is an existing officer delegation within the Council’s Constitution.

Related Meeting

Cabinet - Wednesday 21 October 2026 6.00 pm on October 21, 2026

Supporting Documents

26 Stubbs Avenue. Cabinet report. Reinstate premises following a fire damage. Sep 26. Final draft. V.pdf
Appendix 2. Equality Impact Assessment. 26 Stubbs Avenue. Cabinet report 1.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved
Decision date21 Oct 2026
Effective from27 Oct 2026
Subject to call-inYes