Smethwick to Birmingham Inclusive Growth Corridor - Initial scheme approval
January 17, 2024 Approved View on council websiteFull council record
Content
(1) That approval in principle be
given to the proposed sustainable transport and highway
improvements that make up the Smethwick to Birmingham Inclusive
Growth Corridor Transportation Package as shown on Drawing no.
5216493-ATK-HI-ZZ-DR-D-0113 (attached at Appendix A);
(2) That the Cabinet Member for
Regeneration & WMCA be authorised to approve the carrying out
of public consultation in connection with (1) above;
(3) That any objections received in
connection with (2) above be considered by the Cabinet Member for
Environment & Highways in conjunction with the Cabinet Member
for Regeneration & WMCA at a future Decision Making
Session;
(4) That the Director Regeneration
& Growth be authorised to approve the submission an Outline
Business Case to the West Midlands Combined Authority;
(5) That approval be given for the
Cabinet Member for Environment & Highways to authorise the
Assistant Director-Legal & Assurance in conjunction with
Assistant Director-Highways to enter into an agreement with
Birmingham City Council under section 8 of the Highways Act
1980;
(6) That approval be given for the
land coloured red on Drawing No. SBIGCIMPLINE-001 (attached at
Appendix B) as land comprised within the sites of highways which it
is proposed should be constructed, improved or altered for the
purposes of Schedule 13, paragraph 15 of the Town and Country
Planning Act 1990.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 17 Jan 2024 |