Full council record
Content
(1) That the Interim Director of
Housing be authorised to continue procurement for the HIP Programme
based on previous Cabinet Approval with increased funding to a
total value of £100million;
(2) That the Interim Director of
Housing be authorised to commence the procurement process for the
Domestic Gas Appliance contract;
(3) That approval be given to the
alterations to the delivery model for Social Housing
Decarbonisation Fund (SHDF) Wave 2.1, for Sandwell MBC to act as
Principal Contractor and procure a range of providers for energy
efficiency works;
(4) That the Interim Director of
Housing be authorised to award contracts as set out in (1) to (3)
above to the successful bidders, following a compliant procurement
process that meets Public Contract Regulations 2015 and Sandwell
Corporate Procurement Procedures.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 17 Jan 2024 |