Full council record
Content
13.1
To provide an update on
contract performance for Highways Maintenance between Sheffield
City Council and Amey Hallam Highways (AHH) (subcontracted to Amey
LG (Amey)) as part of a Private Finance Initiative (PFI) contract
dated 31 July 2012 which is due to expire in 2037 (the
Contract).
13.2
RESOLVED
UNANIMOUSLY: That the Waste and Street
Scene Policy Committee:
1.
notes the Amey Contract Performance Report at closed
Appendix 3;
2.
notes the trials on new ways of working for street
cleansing, leafing and planned drainage programmes;
3.
notes that performance with customer responses is
improving and the Authority continues to work with Amey to finalise
an Action Plan; and
4.
notes the areas of improvement to strengthen
monitoring and auditing function.
13.3
Reasons for Decision
13.3.1
The reason for this report is
for the Committee to note the points outlined above and in the
closed Appendix 3 and note Officers proposed way
forward.
13.4
Alternatives Considered and Rejected
13.4.1
The report was for noting,
there were no alternatives considered and rejected.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 13 Mar 2024 |