Attercliffe LUF/Regeneration Framework Progress Update
September 11, 2024 Transport, Regeneration and Climate Policy Committee (Committee) Approved View on council websiteFull council record
Content
10.1
The Senior Development Officer submitted a
report that provided a progress update on the successful Round 1
Levelling Up Fund bid for the Attercliffe Area since 15th November
2023.
10.2
RESOLVED UNANIMOUSLY: That the
Transport, Regeneration and Climate Policy Committee notes the
progress made on the Attercliffe Levelling Up Fund project.
10.3
Reasons for
Decision
10.3.1
This report provides a progress update on the
successful Round 1 Levelling Up Fund bid for Attercliffe Area on
progress since 15th November 2023.
10.4
Alternatives
Considered and Rejected
10.4.1
Do nothing:
Not changing the delivery and development
route for the CCHT would mean that the project couldn’t be
delivered.
10.4.2
Do More:
To do more would require an increase in
funding. This is not currently required to deliver the required LUF
outputs
10.4.3
Chosen Options:
The options in the report represent the best
way of delivering the contracted LUF outputs.
Related Meeting
Transport, Regeneration and Climate Policy Committee - Wednesday 11 September 2024 10.00 am on September 11, 2024
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 11 Sep 2024 |