HRA Revised Capital Programme
September 11, 2025 Cabinet (Cabinet collective) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to approve revisions to the 2025/26 Housing Revenue Account Capital Programme, including the use of £0.400 million from earmarked funding for additional costs to the Heat Network System and an additional £3.348 million prudential borrowing to complete the Spandrel Panel Replacement project.
Full council record
Purpose
To seek approval for the revised Capital
Programme for 2025/26.
Related Meeting
Cabinet - Thursday 11th September 2025 6.00 pm on September 11, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 11 Sep 2025 |
| Subject to call-in | Yes |