2024/25 General Fund Capital Budget Monitoring Report - Qtr1

September 2, 2024 Executive (Other) Key decision Awaiting outcome View on council website
Full council record

Decision

Following consideration of the officer report, appendices and discussion, the Executive resolved to:

a)    Note the contents of the report and appendices.

b)    Approve the slippage of £73.963m from 2024/25 into 2025/26 and beyond whilst a further review of the capital programme takes places during 2024/25.

c)    Approve £11.400m of changes to the capital programme approvals, as detailed in Section 25 of this report.

d)    Approve a £0.528m virement to the capital programme, as detailed in Section 26 of this report.