2025/26 Quarter One Finance update

September 16, 2025 Cabinet (Cabinet collective) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...they noted the forecast revenue position of a £462,000 overspend for the General Fund and a £373,000 surplus for the Housing Revenue Account (HRA), recommended amendments to the HRA Capital Programme to Council for approval, and approved amendments to the Capital Programme requiring Cabinet approval.

Full council record

Purpose

To set out the current financial position for the Council at the end of the first quarter of 2025/26

Decision

1)    That the forecast revenue position of a £462,000 overspend for 2025/26 as detailed in Table 1 and the need for continued focus on the savings and efficiency programme, be noted.

2)    That the forecast revenue position of the HRA for 2025/26 (surplus of £373k) as detailed in Table 3, be noted.

3)    That the amendments to the HRA Capital Programme at Appendix A – Table 4 to take into account the changes set out in this report, be recommended to Council for approval.

4)    That the amendments to the Capital Programme at Appendix B- Table 1c that require Cabinet approval to take into account the changes set out in this report, be approved.

Reasons for the decision

To ensure the Council’s forecast financial position for 2025/26 is considered and related decisions approved. It is important that the Cabinet are aware of the financial position of the General Fund and Housing Revenue Account to ensure that they can make informed decisions that are affordable and financially sustainable for the Council.

Alternative options considered

To not approve the financial movements outlined.

Related Meeting

Cabinet - Tuesday, 16th September, 2025 6.30 pm on September 16, 2025

Supporting Documents

Q1 202526 Forecast Outturn.pdf
Appendix B.pdf
Appendix A.pdf

Details

OutcomeRecommendations Approved
Decision date16 Sep 2025
Effective from25 Sep 2025