Penwortham Masterplan - Kingsfold & Middleforth Approval of Increased Contract Sum
October 5, 2026 Cabinet Member (Planning and Licensing) (Cabinet member) Key decision In call-in window View on council websiteFull council record
Decision
- Approves an increase in the contract sum from £1,210,000 to £1,350,000.
- Approves a contingency of £135,000, equivalent to 10% of the contract sum, to cover potential unforeseen site issues.
- Notes that the increase is required to address additional works identified through the ongoing Section 278 approval process with LCC.
- Notes the Director of Property and Planning has already been authorised to enter the necessary contractual arrangements to the deliver the scheme to construction.
Details
| Reference | Call-ins0 |
| Outcome | Recommendations Approved (subject to call-in) |
| Decision date | 5 Oct 2026 |
| Expected date | 31 Jul 2026 |
| Originally due | 31 Jul 2026 |
| Lead officer | Adam Welsby |
| Subject to call-in | Yes |