Approve Birley Lane Mine Shaft for up to £2m grant

November 12, 2026 Section 73 Officer (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Section 73 Officer approved the recommendation on 12/11/2026. The decision was to approve the appointment of a contractor for mine shaft remediation works, with funding to be managed by the CRSTS Responsive Reserve.

Full council record

Purpose

A request was made to approve the appointment of a contractor to undertake investigation, design and implementation works in response to a mine shaft identified beneath the tram tracks between White Lane and Birley Lane, with an estimated value of up to £2 million.

To facilitate the timely progression of these works, on 11 November 2026, the Investment Board recommended the interim use of the City Region Sustainable Transport Settlement (CRSTS) Responsive Reserve to manage the required remediation works, noting that discussions remain ongoing with the Mining Remediation Authority on funding.
 

Decision

Option 1 – Approve the recommendation

Alternative options considered

1. Approve the recommendation
2. Reject the recommendation
 

Details

OutcomeRecommendations Approved
Decision date12 Nov 2026