Capital Financial Monitoring for the period to the end of December 2024
February 25, 2025 Cabinet (Cabinet collective) Approved View on council websiteFull council record
Purpose
To consider the report of the Cabinet Member
for Finance and Corporate Services providing information on any
major changes in the General Fund and Housing Revenue Account (HRA)
capital programme.
Decision
Cabinet is recommended to:
i)
Note the revised General Fund Capital Programme, which totals
£207.01M as detailed in paragraph 3.
ii)
Note the HRA Capital Programme is £245.53M as detailed in
paragraph 3.
iii)
Approve slippage of £21.97M, £19.75M within the General
Fund programme and £2.21M within the HRA programme, as
detailed in paragraphs 7 to 9 and Appendix 3.
iv)
Note that the overall forecast position for 2024/25 at quarter 3 is
£137.73M, resulting in a potential underspend of
£1.28M, as detailed in paragraphs 10 to 12 and Appendix
2.
v)
Note that the capital programme remains fully funded up to 2028/29
based on the latest forecast of available resources although the
forecast can be subject to change; most notably regarding the value
and timing of anticipated capital receipts and the use of prudent
assumptions of future government grants to be received.
Related Meeting
Budget, Cabinet - Tuesday, 25th February, 2025 4.30 pm on February 25, 2025
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 25 Feb 2025 |
| Subject to call-in | Yes |