Gateway 3 -Variation to Works Contract valued over £500,000 (Works) - Rye Hill

January 22, 2024 Strategic Director of Resources (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve a £3,961,805.34 cost increase to the Rye Hill new build contract with Equans Ltd, revising the contract sum to £10,001,486 and noting a revised completion date of 19 January 2024.

Full council record

Purpose

Approval of cost increase to
main works

Decision

1. 
That the following variations to the Rye Hill new build contract
with Equans Ltd (previously trading as
Engie) totalling £3,961,805.34 be
approved:

 

· 
an additional contract cost for deed of variation of
£2,254,845.93 making the revised contract sum to
£8,294,526.59 from £6,039,680.66 to be executed via a
deed of variation based on the 14 December 2022 position

 

· 
an additional contract cost of £1,706,959.41 for the
additional contract instructions making the revised contract sum
£10,001,486 from £8,294,526.59, of which
£661,790.35 is a retrospective approval

 

2. 
That the revised anticipated contract completion date of 19 January
2024 from 16 May 2022, which is an increase of 86 weeks, be
noted.
 

Details

OutcomeRecommendations Approved
Decision date22 Jan 2024
Subject to call-inYes