Gateway 3 - Variation Decision for variations valued over £500,000 (Works) - Lomond Grove - Deed of Variation to the Works Contracts

November 24, 2023 Strategic Director of Resources (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve a £1,321,561 variation to the works contract with Glenman Corporation Limited for the Lomond Grove development, increasing the contract value to £8,804,964 and noting a revised practical completion date and total scheme costs.

Full council record

Purpose

Approval of cost increase to
main works

Decision

That the Strategic Director of
Finance:
 
1. 
Approves a variation to the works contract for the
development at Lomond Grove with Glenman Corporation Limited (Glenman) from £7,783,403 to £8,804,964
an increase cost of £1,321,561 for the reason noted in
paragraphs 13 -14 (of the report), of which £956,116 is a
retrospective approval.
 
2. 
Notes the revised total scheme costs from
£9,420,681 to £11,212,314 including land acquisition
and on-costs further details of which are in the closed
report.
 
3. 
Notes a revised practical completion date of 22 May
2024, an additional 40 weeks.
 
4. 
Notes an additional variation to the capital
programme in the sum of £436,747 is required for the reason
noted in paragraphs 46-47 (of the report).
 

Details

OutcomeRecommendations Approved
Decision date24 Nov 2023
Subject to call-inYes