Gateway 3 – Cost Variation Decision - Temporary Accommodation - Contract 1
May 23, 2023 Strategic Director of Housing (Officer) Key decision Approved View on council websiteFull council record
Purpose
Approval for variation for cost
increase.
Decision
That the Strategic Director of
Housing:
1.
Formalises his approval of the variation to the
Temporary Accommodation Contract 1, refurbishment/conversion
contract with Niblock (Builders)
Limited (Niblock), varying the contract
sum from £2,086,229 to £2,647,251, an increase of
£561,022.
2.
Approves a variation to the contingency for the
above contract, increasing the contingency from £104,311 to
£132,363, an increase of £28,052.
3.
Notes the increase to estimated on-costs, including a 4% development
allowance associated with the contract, as a
result of the above requested approvals from £371,138
to £403,065 an increase of £31,927.
4.
Notes the increase of the total scheme costs from
£2,561,678 to £3,182,679 resulting to a total scheme
variation of £621,001.
5.
Notes that this report was considered at the
Departmental Contract Review Board (DCRB) in July 2022 but was not
sent for approval until May 2023.
Details
| Outcome | Recommendations Approved |
| Decision date | 23 May 2023 |
| Subject to call-in | Yes |