Gateway 3 - Variation Decision - Temporary Accommodation - Contract 2
May 23, 2023 Strategic Director of Housing (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Strategic Director of Housing approved a variation to the Temporary Accommodation Contract 2 with Niblock (Builders) Limited on 23/05/2023. This decision formalised the approval of an additional £731,907 for the contract, increasing the total sum to £2,615,313, and approved a variation to the contingency fund. The decision also noted increases to other on-costs, development allowance, and total scheme costs.
Full council record
Purpose
Approval for variation for cost increase.
Decision
That the Strategic Director of Housing:
- Formalises his previous approval of the variation to the Temporary Accommodation Contract 2, refurbishment/conversion contract with Niblock (Builders) Limited (Niblock) at an additional cost of £731,907 varying the contract sum from £1,883,406 to £2,615,313.
- Approves a variation to the contingency for the above contract, increasing the sum by £36,596, varying the contingency from £94,170 to £130,766.
- Notes the increase to the other on-costs, and 4% development allowance associated with the contract, from £247,691 to £528,318 resulting in a variance of £280,627.
- Notes the increase of the total scheme costs from £2,225,267 to £3,274,397, resulting in an increase of £1,049,130.
- Notes that this report was considered at Departmental Contract Review Board (DCRB) in July 2022 but was not sent for approval until April 2023.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 23 May 2023 |
| Effective from | 1 Jun 2023 |
| Subject to call-in | Yes |