GW2 - Leisure Centre retrofit design
May 21, 2025 Strategic Director of Environment, Sustainability and Leisure (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to award Eddisons a £1,081,972.25 contract for leisure centre decarbonisation design work through RIBA 4, and to approve the associated variation to the scope of works.
Full council record
Purpose
To award the contract to
appoint a contractor to undertake retrofit design work on leisure
centres
Decision
That:
1.
The award of the Leisure Centres Decarbonisation
Designs contract to Eddisons to the sum
of £1,081,972.25. This sum will cover design through to RIBA
4 (detailed design and technical specification) as well as
associated design oversight and quality assurance through the
installation and delivery period, to practical completion be
approved by the Strategic Director of Environment, Sustainability
and Leisure.
2.
The associated variation to the scope of works from
that noted at Gateway 1, to cover more phases of the project in
order to derisk the programme (a variation that occurred based on
additional professional advice which the Gateway 1 agreed to seek,
and before the tender process took place) be noted and approved by
the Strategic Director of Environment, Sustainability and
Leisure.
Details
| Outcome | Recommendations Approved |
| Decision date | 21 May 2025 |
| Subject to call-in | Yes |