Gateway 3 – Highways Works contract extension
September 24, 2025 Cabinet Member for Clean Air, Streets and Waste (Cabinet member) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to extend the Southwark Highways Works Contract with FM Conway Ltd for an additional year from April 1, 2026, at an estimated cost of £12,000,000 to ensure continued delivery of highway improvements.
Full council record
Purpose
This to enable the delivery of Streets for
People and Highway programme and to avoid the possible clash with a
new contractor having to be mobilised before council election in
May 2026. Giving time for a full review of the contracts and
allowing for the procurement process.
Decision
The Cabinet Member for Clean Air,
Streets and Waste approved the variation
of the Southwark Highways Works Contract with FM Conway Ltd (Lot A
– Reactive maintenance and small scale reactive repair works)
(Lot B – Planned improvement or renewal works to our
highways), for an additional one year period from 1 April 2026 at
an estimated total cost of £12,000,000 (£2.45m for Lot
A and £9.55m for Lot B) in order to deliver highways works to
support the delivery of highway improvements as part of Lots A and
B of the Southwark Highways Works Contract 2020-26.
Details
| Outcome | Recommendations Approved |
| Decision date | 24 Sep 2025 |
| Subject to call-in | Yes |