...approved the variation of the Communal Lighting and Electrical Testing Contracts A and B to extend their terms for seven months, from February to August 2026, to ensure continued service delivery while new procurement exercises are completed.

Full council record

Purpose

To extend the current contracts
with BCS (Electrical and Building) Ltd  & Spokemead Maintenance Ltd whilst a new procurement
exercise is carried out and completed.

Decision

That the Strategic Director of
Housing;
 
1. 
Approves the variation of the Communal Lighting and
Electrical Testing Contract A (north of the borough) to BCS (Electrical and Building) Ltd. to extend the term of the contract for an
additional period of seven-months from 1 February 2026 to 31
August 2026 at an estimated additional sum of £10.44m making
a total revised estimated contract value of £50.80m.
 
2. 
Approves the variation of the Communal
Lighting and Electrical Testing Contract B
(south of the
borough) to Spokemead Maintenance
Ltd. to extend the term of
the contract for an additional period of seven-months from 1 February 2026 to 31 August 2026 at an
estimated additional sum of £11.57m making a total revised
estimated contract value of £56.55m.
 
3. 
Notes that the annual Building Maintenance Indices
(BMI) rise, which is due in April 2026, will be applied to both
Contracts A and B as agreed in principle with BCS (Electrical and
Building) Ltd. and Spokemead Maintenance Ltd., and
this will be evidenced in a deed of variation for these
extensions.
 
4. 
Notes that the Leader delegated the decision of
this Gateway 3
report to the
Strategic Director of Housing via a Notice of Variation dated 15
September 2025.
 
 
 

Supporting Documents

Appendix 1 - Equality Needs Impact Assessment.pdf
Report Gateway 3 Variation of Communal Lighting and Electrical Testing Contracts - Contract A No.pdf

Details

OutcomeRecommendations Approved
Decision date26 Feb 2026
Subject to call-inYes