Gateway 2 Leisure Decarbonisation Capital Works Procurement – Peckham Pulse
August 3, 2026 Strategic Director of Environment, Sustainability and Leisure (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Strategic Director of Environment, Sustainability and Leisure approved the award of a contract to Alternative Heat Ltd for decarbonisation works at Peckham Pulse Leisure Centre for £2,267,249.96. This decision was made on 03/08/2026. The decision includes the removal of the existing gas-fired heating system and the provision of low-carbon energy systems.
The Leader of the Council approved the implementation of a raised zebra crossing and footway build-outs on Half Moon Lane. This decision was made in July 2026. The decision includes instructing officers to write to objectors, proceed with implementation, and make the necessary Traffic Management Order.
The Executive Member for Council Homes approved the payment of £32,056 in Getting Involved Grants to various resident and community groups. This decision was made on 27/07/2026.
Full council record
Purpose
To award the contract to appoint a contractor to undertake decarbonisation capital works to Peckham Pulse Leisure Centre
Decision
- That the award of the Leisure Centres Decarbonisation works contract for the Peckham Pulse Leisure Centre to Alternative Heat Ltd in the sum of £2,267,249.96 (excluding VAT) be approved. This sum includes the full decarbonisation of Peckham Pulse Leisure Centre through the removal of the existing gas-fired heating system and the provision of low-carbon energy systems.
- That the associated variation to the scope of works from that noted at Gateway 1, to cover more phases of the project in order to derisk the programme (a variation that occurred based on additional professional advice which the Gateway 1 agreed to seek, and before the tender process took place), be noted and approved.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 3 Aug 2026 |
| Effective from | 11 Aug 2026 |
| Lead officer | Clive Palfreyman |
| Subject to call-in | Yes |