Gateway 2 Leisure Decarbonisation Capital Works Procurement – Camberwell

September 29, 2026 Strategic Director of Environment, Sustainability and Leisure (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Strategic Director of Environment, Sustainability and Leisure approved the award of the Leisure Centres Decarbonisation works contract for Camberwell Leisure Centre to Alternative Heat Ltd. for £2,794,350.20 (excluding VAT) on 29/09/2026. This decision includes the full decarbonisation of the centre through the removal of the existing gas-fired heating system and the provision of low-carbon energy systems. The decision also approved a variation to the scope of works from Gateway 1 to derisk the programme.

Full council record

Purpose

To award the contract to appoint a contractor to undertake decarbonisation capital works to Camberwell Leisure Centre (subject to planning permission)

Decision

  1. That the award of the Leisure Centres Decarbonisation works contract for Camberwell Leisure Centre to Alternative Heat Ltd. in the sum of £2,794,350.20 (excluding VAT), be approved. This sum includes the full decarbonisation of Camberwell Leisure Centre through the removal of the existing gas-fired heating system and the provision of low-carbon energy systems.
  2. That it be noted and approved that the associated variation to the scope of works from that noted at Gateway 1, to cover more phases of the project in order to derisk the programme (a variation that occurred based on additional professional advice which the Gateway 1 agreed to seek, and before the tender process took place).

Supporting Documents

GW2 Leisure Decarb Capital Works Procurement - Camberwell.pdf

Details

OutcomeRecommendations Approved
Decision date29 Sep 2026
Effective from7 Oct 2026
Lead officerDavid Quirke-Thornton
Subject to call-inYes