Gateway 3 - Variation Decision - Extension of the South East London Combined Heat and Power plant (SELCHP) Heat Network to the Tustin Estate

November 8, 2024 Strategic Director of Resources (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve a £6,530,621 contract variation with Veolia Environmental Services Southwark Limited to extend the South East London Combined Heat and Power plant heat network to the Tustin Estate redevelopment, including capital expenditure and heat purchase through 2033.

Full council record

Purpose

To vary the current contract
with Veolia Environmental Services Southwark Limited to extend the
heat network to the Tustin Estate redevelopment.

Decision

The Strategic Director of
Resources approved the proposed variation to the council’s
Heat Supply Agreement with Veolia ES Southwark Limited (VESS) for
Works which requires capital expenditure from the council of
£5,050,259 and the purchase of heat from VESS to 2033 at a
cost of £1,480,362 making a total variation value of
£6,530,621.
 
 
 
 

Details

OutcomeRecommendations Approved
Decision date8 Nov 2024
Subject to call-inYes