Replacement of Mechanical & Electrical Plant at Sunbury Leisure Centre
December 9, 2024 Corporate Policy and Resources Committee, Council (Committee) Key decision Approved View on council websiteFull council record
Content
The Committee resolved to:
1.
Approve a net budget of up to £739,000 to undertake
improvement mechanical and electrical plant replacement works at
Sunbury Leisure Centre,
2.
Approve a contingency budget in the amount that equals 10% of the
total project cost,
3.
Delegate authority to the Group Head of Assets in consultation with
the Chair and Vice Chair of the Corporate Policy & Resources
Committee to agree requests for expenditure from the contingency
budget,
4.
Delegate authority to the Group Head of Assets in consultation with
the Chair and Vice Chair of Corporate Policy & Resources
Committee to appoint the preferred bidder as set out in this report
to undertake the mechanical and electrical plant works; and
5.
Delegate authority to the Group Head of Corporate Governance to
enter into necessary legal documentation to formalise the
appointment of the Contractor.
Related Meeting
Corporate Policy and Resources Committee - Monday, 9 December 2024 7.00 pm on December 9, 2024
Details
| Outcome | Recommendations Approved |
| Decision date | 9 Dec 2024 |