Contract for ILMP works at AshwellHouse, Painswick
August 18, 2025 Head of Property Services (Officer) Approved View on council websiteFull council record
Purpose
To enable the council to complete works to
this scheme it is necessary to enter into a contract with a
contractor. The Procurement of this programme of works was
undertaken via the Westworks DPS in 2022, with the option of direct
awarding up to a further 9 schemes.
Decision
To enter into a contract with EW Beard for the
improvement works at Ashwell House, Painswick
Reasons for the decision
none
Alternative options considered
Option 1 - Re procure the works. This was
rejected as the contractor continues to complete works on schedule
and within budget, satisfaction continues to be very high with all
KPIs achieving scores of 9 out of 10 or higher.
A cost consultant has confirmed that the cost estimate represents
value for money.
Option 2 - don't carry out the works. This was rejected as this
programme and budget for it has been approved and continues to be
supported by Housing Committee.
Details
| Outcome | Recommendations Approved |
| Decision date | 18 Aug 2025 |