M5 Crossing Dewatering Contract
June 5, 2026 Strategic Director of Place (Officer) Approved View on council websiteFull council record
Purpose
Dewatering is one of the key projects for the M5 Crossing Project. Pump Supplies were the highest scoring tender submission and have been awarded the contract following the SDC procurement process and evaluation methodology.
Decision
Authorise the issue of the Dewatering Contract to Pump Supplies Ltd following SDC procurement process.
Reasons for the decision
The Strategic Leadership Team have been kept updated on the M5 Crossing Project.
Alternative options considered
There is no alternative option. The M5 Crossing project has been has been approved by the CCC Project Board. SDC as Accountable Body are responsible for delivering the project. Not awarding this contract will require for the M5 Crossing Project to be placed on hold.
Details
| Outcome | Recommendations Approved |
| Decision date | 5 Jun 2026 |