Capital Plan Updates
December 17, 2024 Director of Finance (Officer) Approved View on council websiteFull council record
Decision
i)
That Crossways be progressed through to the next stage of design,
inclusive of planning, and a budget of £1,300,000 from the
£2,000,000 ring fenced adult social care funds, as approved
through a published Record of Decision on the 18 September 2019, be
released to carry out this work ;
ii)
That Collaton St Mary Flood Alleviation
project be progressed through to the next stage of design and for a
budget of £117,650 to be included within the Capital plan
from the identified Section 106 Legal Agreement and Environment
Agency grant funding;
iii)
That Brixham Public Realm project be progressed through to the next
stage of design and consultation and for the project to be included
within the Capital Plan with an initial allocation of £75,000
from the Levelling Up grant funds.
Details
| Outcome | Recommendations Approved |
| Decision date | 17 Dec 2024 |