Local Electric Vehicle Infrastructure (LEVI)
March 18, 2025 Cabinet (Cabinet collective) Approved View on council websiteFull council record
Decision
That the Divisional
Director for Planning, Housing and Climate Emergency, be given
delegated authority to award the concession contract and associated
land agreements, to be undertaken in accordance with advice and
guidance provided by the Devon County Council procurement team and
Torbay Council’s Commercial and Legal Services for delivery
of the programme up to the value of the capital grant funding
awarded.
Reasons for the decision
To progress the
spending and meet our obligations and conditions of the grant
funding, it is necessary to delivery on the commitment to
delivering Electric Vehicle Infrastructure to support the
transition to electric vehicles. To
achieve the delivery of the Electric Vehicle Infrastructure there
was a need to award concession contracts and in certain
circumstances land agreements.
Alternative options considered
Not to approve
delegated authority to award the contract, this option was
discounted as it would slow down progress and result in a
complicated governance process with separate contracts for each lot
utilised and land agreements for sites as necessary. Devon County Council would continue with their
elements, though there would be some risk associated with that
should Torbay Council at a later date,
not award the contract.
Not to award the
contract(s), the Council would likely be required to return the
funding to the Office for Zero Emission Vehicles and some of the
LEVI revenue funding awarded to support capacity alongside may also
be clawed back.
The Council could
choose to re-run a procurement process separate from Devon, but
this would compromise the Devon led procurement to date and likely
result in less positive value for money outcome. Furthermore, this would slow the adoption of
electric vehicles and not provide the support to the community to
help in the transition, providing choice about travel and making it
harder to meet national and local climate commitments.
Details
| Outcome | Recommendations Approved |
| Decision date | 18 Mar 2025 |
| Effective from | 29 Mar 2025 |
| Subject to call-in | Yes |