APPROVAL OF SPEND TO DELIVER THE REQUIREMENTS OF RIBA STAGES 3 TO 4 AND AWARD OF CONTRACT AND APPROVAL OF SPEND FOR CLIENT-SIDE PROJECT AND COST MANAGEMENT SERVICES FOR THE REFURBISHMENT AND NEW BUILD EXTENSIONS AT YSGOL BRYN ONNEN

August 18, 2025 Acting Joint Director - Economy and Place (Other) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

...to approve spending £584k for Kier Construction Ltd to deliver RIBA stages 3 and 4 and to award a £95k contract to Gleeds Management Service Ltd for project and cost management services, both related to the refurbishment and new build extensions at Ysgol Bryn Onnen.

Full council record
Content

To seek approval for the spend of £584k
to Kier Construction Ltd to deliver Riba stages 3 and 4 as part of
the pre-construction phase of the refurbishment and new build
extensions at Ysgol Bryn Onnen at a cost of £584k

To seek approval for the Award of Contract to Gleeds Management
Service Ltd (Gleeds) to deliver client-side project and cost
management services for the pre-construction phase of the
refurbishment and new build extensions at Ysgol Bryn Onnen at a
cost of £95k.

Supporting Documents

APPROVAL OF SPEND TO DELIVER THE REQUIREMENTS OF RIBA STAGES 3 TO 4 AND AWARD OF CONTRACT AND APPROV.pdf
EP007 Report award of contract for YBO 10 07 25.docx.pdf

Details

OutcomeRecommendations Approved
Decision date18 Aug 2025