Civic Quarter Heat Network - Approval to Accept Green Heat Network Fund Grant

December 18, 2024 Executive (Other) Awaiting outcome View on council website
Full council record

Decision

(1)      
That the contents of the report, be
noted.

 
(2)      
That the Executive approves accepting the grant if
Trafford Council’s application is successful, and moving to
the commercialisation phase of work, noting that a final decision
to proceed will be taken once this phase has completed.
 
(3)      
That the Corporate Director of Place, in
consultation with the Director of Finance and the Director of Legal
and Governance, be delegated authority to accept the Green Heat
Network Fund grant if awarded at the level submitted.
 
(4)      
That the Corporate Director of Place, following
consultation with finance, legal and procurement, be delegated
authority to carry out a procurement exercise to identify
commercialisation advisers and a third-party delivery partner, and
take all other necessary steps to develop the project prior to
approval of a Joint Development Agreement.
 
(5)      
That a further report be made to the Executive to
seek approval of the Joint Development Agreement.

Related Meeting

Executive - Wednesday, 18th December, 2024 6.30 pm on December 18, 2024

Supporting Documents

CQ heat network_Exec Report_Dec 2024.pdf

Details

OutcomeFor Determination
Decision date18 Dec 2024
Effective from4 Jan 2025
Subject to call-inYes