Purpose
Request for funds to complete works to the
landfill and budget for fees to progress a larger project in the
future.
Content
That the Executive approves:
1.
A
project to repair the existing monitoring solution at Weydon Lane, to enable the site to be fully
monitored for gas and groundwater quality, by bringing compromised
vents and monitoring wells back into use.
2. A
supplementary estimate of £65,000 required for construction
costs and the appointment of consultants to support the
redevelopment of the site.
That the Executive
endorses:
3. The intention to
redevelop the site in the long-term for recreational and leisure
use.