To award the extension of consultants’ contracts to develop the amended design up to RIBA stage 3 in preparation for business case approval and the planning submission, for the residential development project at 69 High Street

January 20, 2026 Joint Strategic Director - Finance (S151) (Officer) Approved View on council website
Full council record
Content

To award the extension of contracts for the
design team to develop the amended housing scheme that will deliver
up to 13 affordable homes to residents in Waverley.
Total value of the contracts’ variations: £36,199

Reasons for the decision

To ensure continuity of service

Alternative options considered

That the contracts are not extended and the
final design team work cannot be completed.

Details

OutcomeRecommendations Approved
Decision date20 Jan 2026