Bath Walking Wheeling and Cycling Links

June 5, 2026 Executive Director of Transport (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved the Bath Walking Wheeling and Cycling Links (Kennet & Avon Canal Route) Full Business Case on 05/06/2026. This approval included the drawdown of £1,837,582 of City Region Sustainable Transport Settlement capital funding to Bath & North East Somerset Council for delivery. The decision also noted the £459,395 match funding allocation from Bath & North East Somerset Council.

Full council record

Decision

The Executive Director of Transport:

1)    Approves the Bath Walking Wheeling and Cycling Links (Kennet & Avon Canal Route) Full Business Case.

2)    Approved the drawdown of £1,837,582 of City Region Sustainable Transport Settlement (CRSTS) capital funding to Bath & North East Somerset Council to deliver the Kennet & Avon Canal Route as shown below:

Pre 2025/26

2025/26

2026/27

2027/28

Total

Full Business Case Development (CRSTS)

£371,159

£81,269

£452,428

Delivery match funding

£459,395

£459,395

Delivery CRSTS Grant

£1,837,582

£1,837,582

Total

£2,749,405

3)    Notes the £459,395 Bath & North East Somerset Council match funding allocation to the Bath Walking Wheeling and Cycling Links (Kennet & Avon Canal Route).

Supporting Documents

Item 10 - Delivery Assurance.pdf
Item 19 - Corporate Risk Framework.pdf
Transport Infrastructure Projects.pdf
123 Zero Emissions Transport City_July 2026_Executive Director of Transport.pdf
Item 10 - Delivery Assurance.pdf
ODN Skills Bootcamps Funding Allocation and Delivery Plan 1.pdf
Employment Land Strategic Needs Assessment Contract.pdf
South Gloucestershire Council CRSTS Programme - Reprofiling Funds FY25-26.pdf
Publication of the West of England Local Remediation Acceleration Plan LRAP and Grant Allocations.pdf
Item 19 - Corporate Risk Framework.pdf
Low Carbon Business Support Green Business Grants.pdf
Low Carbon Business Support Green Business Grants.pdf
Adult Skills Fund - Final Allocations for 2026-27.pdf
Adult Skills Fund - Final Allocations for 2026-27.pdf
Bath Walking Wheeling and Cycling Links.pdf
West Innovation Arc New Town Communications Support.pdf
Bus Information Review.pdf
Publication of the West of England Local Remediation Acceleration Plan LRAP and Grant Allocations.pdf
Bus Information Review.pdf
Transport Infrastructure Projects.pdf
122 Consolidated Active Travel Fund ATF6 Correction_July 2026_Executive Director of Transport.pdf
122 Consolidated Active Travel Fund ATF6 Correction_July 2026_Executive Director of Transport.pdf
Bath Walking Wheeling and Cycling Links.pdf
123 Zero Emissions Transport City_July 2026_Executive Director of Transport.pdf
West Innovation Arc New Town Communications Support.pdf
Future Bus Network and Active Travel Gap Analysis Studies Feasibility Development Application Form.pdf
Future Bus Network and Active Travel Gap Analysis Studies Feasibility Development Application Form.pdf

Details

OutcomeRecommendations Approved
Decision date5 Jun 2026