Getting About in Thornbury (Amended)

September 17, 2026 Executive Director of Transport (Officer) Key decision Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved the Getting About in Thornbury Full Business Case and the drawdown of £2,168,372 of CRSTS capital funding to South Gloucestershire Council. The decision was made on 17/09/2026. The Executive Director also approved the drawdown of £500,000 Economic Development Fund funding.

The West of England Mayoral Combined Authority Committee endorsed the joint Masterplan for Hicks Gate as a non-statutory planning framework to inform emerging planning policy on 05/06/2026. This masterplan aims to unlock coordinated and high-quality housing delivery with significant infrastructure delivery.

The Head of Housing and Strategic Planning awarded a contract worth £67,500 plus VAT to College Green Group for a targeted political and policy engagement campaign to support the Brabazon and West Innovation Arc new towns bid to Government on 12/06/2026.

The Executive Director of Transport approved the West of England Future Bus Network and Active Travel Gap Analysis Studies Feasibility and Development Funding Application and awarded £33,000 of Transport for City Regions revenue funding for 2026/27 on 05/06/2026.

The Executive Director for Transport awarded a contract of £316,500 (excluding VAT) to Womble Bond Dickinson (UK) LLP for legal services for land acquisition for the Bath to Bristol Strategic Corridor programme on 05/06/2026.

The Director of Bus Operations awarded a contract for the WESTlink Call Centre to Constellia Public Limited for up to one year with a maximum value of £201,600 on 02/04/2026.

The CEO awarded a contract for Henbury Station detailed design and further design work on the Henbury line upgrade to Network Rail for a total of £6,764,379 on 26/05/2026.

The West of England Mayoral Combined Authority Committee agreed to note committee membership, agree terms of reference for its main committee and revised terms for the Overview and Scrutiny and Audit Committees, note the appointment of a Deputy Mayor, agree membership arrangements for committees and advisory boards, agree to appoint independent members to the Audit Committee, agree that committee chairs can address meetings, agree the schedule of meetings, and approve the Pay Policy Statement on 05/06/2026.

Full council record

Decision

*To note this is an amendment to decision reference 25_178 to correct the CRSTS Development funding from £458,000 to £462,118 and the approved CRSTS funding drawdown from £2,172,490 to £2,168,372.

That the Executive Director of Transport:

1)     Approved the Getting About in Thornbury Full Business Case

2)     Approved the drawdown of £2,168,372 of City Region Sustainable Transport Settlement (CRSTS) capital funding to South Gloucestershire Council to deliver the Getting About in Thornbury scheme with the profile set out below:

That the Chief Executive Officer:

3)     Approves the drawdown of £500,000 Economic Development Fund (EDF) funding with the profile set out below:

Up to 2026/27

2027/28

2028/29

Total

CRSTS Development

£462,118

£462,118

CRSTS Delivery

574,143

£ 1,569,229

£25,000

£2,168,372

EDF

£500,000

£ 500,000

Total

£1,036,261

£2,069,229

£25,000

£ 3,130,490

Supporting Documents

1. Annual Business Report.pdf
APPENDIX 1 committee membership ABR.pdf
APPENDIX 2 - Terms of Reference - Main Committee ABR.pdf
APPENDIX 3 ToR amendments Overview and Scrutiny ABR.pdf
APPENDIX 4 Amended Scrutiny ToR Tracked and Clean 27.04.26 ABR.pdf
APPENDIX 6a Audit Committee ToR v22.05.26 Clean ABR.pdf
APPENDIX 7 Pay Policy Statement 26-27.pdf
West Innovation Arc New Town Communications Support.pdf
Item 18 - Hicks Gate Masterplan.pdf
Future Bus Network and Active Travel Gap Analysis Studies Feasibility Development Application Form.pdf
109 Henbury Station Design_May 2026_CEO.pdf
Bath to Bristol Strategic Corridor - Legal Services for Land Acquisition Contract.pdf
Delegated use of 1m revenue funding from MHCLG to support the expansion of the WECA.pdf
Item 13 - Skills Strategy.pdf
Item 13A - West of England Skills Strategy.pdf
Item 21 - OS Annual Report.pdf
Item 21A - Appendix 1 ANNUAL REPORT OS Committee.pdf
Visit West Implementation Plan 2026-2027.pdf
110 WESTlink Call Centre contract_Apr 26_Director of Bus Ops.pdf
Item 08 - MCA Mayoral Budget Outturn.pdf
Getting About in Thornbury.pdf
Item 18a - Appendix Hicks Gate Framework Masterplan.pdf
APPENDIX 6 Audit committee ToR v22.05.26 Tracked ABR.pdf
APPENDIX 8 - Draft - 26-27 municipal calendar.pdf
APPENDIX 5 ToR amendments Audit Committee ABR.pdf
125 Hydrogen and Sustainable Transport Economy Accelerator_July 2026_Executive Director of Transport.pdf

Details

OutcomeRecommendations Approved
Decision date17 Sep 2026