CRSTS Bristol Programme re-baselining June 26

August 19, 2026 Executive Director of Transport (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Executive Director of Transport approved changes to the Bristol City Regions Sustainable Transport Settlement Programme milestones and grant awards on 19/08/2026. The decision also approved the reprofiling of CRSTS spend and Investment Fund funding for the Muller Road project, and the Chief Executive Officer approved bringing forward Economic Development Fund funding for the Harbour Walkway scheme.

Full council record

Decision

That the Executive Director of Transport:

1)      Approves the milestone changes to the Bristol City Regions Sustainable Transport Settlement Programme as shown below:

Key milestones 

Baseline milestones construction starts 

Proposed change 

Baseline milestones construction end 

Proposed change 

Delay (by months) 

East Bristol Liveable Neighbourhood

10/2026

03/2027

03/2027

01/2028

5 & 10

CC -Bedminster Bridges

07/2026

01/2027

08/2027

07/2028

6 & 10

CC - Redcliffe Roundabout

07/2026

01/2027

08/2027

07/2028

6 & 10

CC - Union Street

08/2026

02/2027

11/2027

03/2028

6 & 4

CC - Bond St

04/2027

06/2027

NA

NA

2

A37/A4018 - WP4 Stockwood area

03/2027

07/2027

07/2027

12/2027

4 & 5

A37/A4018 – WP4 Crow Lane

03/2027

07/2027

07/2027

12/2027

4 & 5

A37/A4018 - WP2 Southern Section

NA

NA

07/2026

04/2027

9

A37/A4018 – WP1 Victoria St

NA

NA

06/2026

10/2026

4

Baseline closure date 

Proposed change 

Bristol Bridge

03/2027

09/2027

6

FBC date 

Construction start date 

Construction end date 

StreetSpace 2 Rosemary Lane

10/2026

02/2027

08/2027

6 & 7 & 2

Baseline FBC date 

Proposed change 

Delay by months 

StreetSpace 2 Denmark St

04/2026

08/2026

4 

Bond Street

06/2026

11/2026

5

A37/A4018 WP4- Stockwood

08/2026

01/2027

5

A37/A4018 WP4 – Crow Lane

08/2026

02/2027

6

SBLN

09/2025

02/2027

17

A37/A4018 WP5

01/2027

06/2027

5

2) Approves the changes to the CRSTS grant awards for the following projects within the Bristol City Regions Sustainable Transport Settlement Programme:

Scheme

Grant

Current Award

Updated Award

Difference

A38 South MetroBus Extension

CRSTS BG

£2,905,000

£2,906,842

£1,842

Bristol Bridge

CRSTS M

£1,379,192

£1,373,832.70

-£5,359.30

Bedminster Green

CRSTS N

£9,771,217

£9,772,712

£1,495

Temple Way

CRSTS BB

£2,152,086

£2,760,537

£608,451

WP1- Victoria Street/Colstone Avenue

CRSTS AI

£5,565,143

£5,548,448

-£16,695

3) Approves the reprofile of CRSTS spend across the remaining delivery years as listed in Appendix 1.

4) Approves the reprofile of £22,442 of Investment Fund (IF) funding for Muller Road project from FY26/27 to FY25/26 as list in Appendix 1.

That the Chief Executive Officer: 

5) Approves bringing forward £15k of Economic Development Fund (EDF) from FY 26/27 to FY 25/26 for the Harbour Walkway scheme.

Supporting Documents

CRSTS Bristol Programme re-baselining June 26.pdf

Details

OutcomeRecommendations Approved
Decision date19 Aug 2026