CRSTS Bristol Programme re-baselining June 26
August 19, 2026 Executive Director of Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Executive Director of Transport approved changes to the Bristol City Regions Sustainable Transport Settlement Programme milestones and grant awards on 19/08/2026. The decision also approved the reprofiling of CRSTS spend and Investment Fund funding for the Muller Road project, and the Chief Executive Officer approved bringing forward Economic Development Fund funding for the Harbour Walkway scheme.
Full council record
Decision
That the Executive Director of Transport:
1) Approves the milestone changes to the Bristol City Regions Sustainable Transport Settlement Programme as shown below:
Key milestones
Baseline milestones construction starts
Proposed change
Baseline milestones construction end
Proposed change
Delay (by months)
East Bristol Liveable Neighbourhood
10/2026
03/2027
03/2027
01/2028
5 & 10
CC -Bedminster Bridges
07/2026
01/2027
08/2027
07/2028
6 & 10
CC - Redcliffe Roundabout
07/2026
01/2027
08/2027
07/2028
6 & 10
CC - Union Street
08/2026
02/2027
11/2027
03/2028
6 & 4
CC - Bond St
04/2027
06/2027
NA
NA
2
A37/A4018 - WP4 Stockwood area
03/2027
07/2027
07/2027
12/2027
4 & 5
A37/A4018 – WP4 Crow Lane
03/2027
07/2027
07/2027
12/2027
4 & 5
A37/A4018 - WP2 Southern Section
NA
NA
07/2026
04/2027
9
A37/A4018 – WP1 Victoria St
NA
NA
06/2026
10/2026
4
Baseline closure date
Proposed change
Bristol Bridge
03/2027
09/2027
6
FBC date
Construction start date
Construction end date
StreetSpace 2 Rosemary Lane
10/2026
02/2027
08/2027
6 & 7 & 2
Baseline FBC date
Proposed change
Delay by months
StreetSpace 2 Denmark St
04/2026
08/2026
4
Bond Street
06/2026
11/2026
5
A37/A4018 WP4- Stockwood
08/2026
01/2027
5
A37/A4018 WP4 – Crow Lane
08/2026
02/2027
6
SBLN
09/2025
02/2027
17
A37/A4018 WP5
01/2027
06/2027
5
2) Approves the changes to the CRSTS grant awards for the following projects within the Bristol City Regions Sustainable Transport Settlement Programme:
Scheme
Grant
Current Award
Updated Award
Difference
A38 South MetroBus Extension
CRSTS BG
£2,905,000
£2,906,842
£1,842
Bristol Bridge
CRSTS M
£1,379,192
£1,373,832.70
-£5,359.30
Bedminster Green
CRSTS N
£9,771,217
£9,772,712
£1,495
Temple Way
CRSTS BB
£2,152,086
£2,760,537
£608,451
WP1- Victoria Street/Colstone Avenue
CRSTS AI
£5,565,143
£5,548,448
-£16,695
3) Approves the reprofile of CRSTS spend across the remaining delivery years as listed in Appendix 1.
4) Approves the reprofile of £22,442 of Investment Fund (IF) funding for Muller Road project from FY26/27 to FY25/26 as list in Appendix 1.
That the Chief Executive Officer:
5) Approves bringing forward £15k of Economic Development Fund (EDF) from FY 26/27 to FY 25/26 for the Harbour Walkway scheme.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Aug 2026 |