MetroWest Phase 1 - Funding Reprofile and Programme Re-Baseline
August 19, 2026 Executive Director of Transport (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Executive Director of Transport approved the re-profiling of funding for MetroWest Phase 1 and re-baselined programme milestones on 19/08/2026. The Chief Executive Officer also approved the re-profiling of the Economic Development Fund for the project on the same date. This included changes to capital funding allocations and programme milestones for the project.
Full council record
Decision
That the Executive Director for Transport:
- Approves the re-profiling of the City Region Sustainable Transport Settlement (CRSTS) and Investment Fund (IF) associated with the MetroWest Phase 1 project, as per table below;
Funding Re-profile (in £m)
FY 25/6
FY 26/27
FY 27/28
FY 28/29
Total
CRSTS
Previous
£6.436m
£20.780m
£0.000m
£0.000m
£27.216m
Current
£5.755m
£5.880m
£15.587m
£0.000m
£27.216m
Movement
-£0.681
-£14.901m
£15.587m
£0.000m
£0.000m
Investment
Fund
Previous
£0.000m
£0.000m
£9.657m
£0.000m
£9.657m
Current
£0.000m
£0.000m
£0.000m
£9.657m
£9.657m
Movement
£0.000m
£0.000m
-£9.657m
£9.657m
£0.000m
Note: above are changes to capital funding only, there are no changes to revenue funding.
- Approves the re-baselined programme milestones associated with the MetroWest Phase 1 project, as per table below;
Change to Milestones
Previous Approved
Current Proposed
Variance
Completion of Detail Design
22/12/2026
05/02/2027
1 month
Start of Main Construction Works
26/09/2025
28/04/2026
7 months
All Site Construction Works Completed
31/12/2027
06/06/2028
5 months
Scheme Opening and Start of Train service
31/03/2028
06/12/2028
8 months
Scheme Hand-back (Defect Liability)
31/03/2029
06/12/2029
8 months
That the Chief Executive Officer:
- Approves the re-profiling of the Economic Development Fund (EDF) associated with the MetroWest Phase 1 project, as per table below;
Funding Re-profile (in £m)
FY 25/6
FY 26/27
FY 27/28
FY 28/29
Total
Economic Development Fund
Previous
£0.000m
£33.327m
£19.203m
£0.000m
£52.530m
Current
£0.000m
£0.000m
£52.530m
£0.000m
£52.530m
Movement
£0.000m
-£33.327m
£33.327m
£0.000m
£0.000m
Note: above are changes to capital funding only, there are no changes to revenue funding
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 19 Aug 2026 |