SUSTAINABLE INNOVATIVE FINANCIAL FOUNDATIONS FOR TURBINES CHANGE REQUEST
August 24, 2026 Director of Operations (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Director of Operations, West of England Combined Authority, approved changes to the Bristol Energy Network's Sustainable Innovative Financial Foundations for Turbines project on 24/08/2026. The decision approved changes to project milestones and dates, extending the completion date to January 2027. This included changing two milestones by five months, removing two milestones outside the grant scope, and altering the project completion date by five months.
Full council record
Decision
That the Director of Delivery and Operations, in consultation with Directors, approves the changes to Bristol Energy Network’s Sustainable Innovative Financial Foundations for Turbines project, that:
- the proposed changes to the milestones and dates which will allow the project to meet deliverables and complete the project by the end of January 2027. As set out in the table below.
· To change two milestones by 5 months, from July 26 to December 26
· To remove two milestones that fall outside of the scope of the grant scope
· To change the completion date by 5 months from August 26 to January 27
Milestone changes
Milestone
Last Reported
Proposed
Planning permission applications submitted
July 26
December 26
Funding in Principle and Due Diligence commencement
July 26
Remove milestone – Falls outside of grant scope.
Financial Close on wind turbine projects
July 26
Remove milestone – Falls outside of grant scope.
Stage 5 Completed
July 26
December 26
Evaluation and project close out
August 26
January 27
Project Completion
08/26
01/27
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 24 Aug 2026 |