SUSTAINABLE INNOVATIVE FINANCIAL FOUNDATIONS FOR TURBINES CHANGE REQUEST

August 24, 2026 Director of Operations (Officer) Approved View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

Director of Operations, West of England Combined Authority, approved changes to the Bristol Energy Network's Sustainable Innovative Financial Foundations for Turbines project on 24/08/2026. The decision approved changes to project milestones and dates, extending the completion date to January 2027. This included changing two milestones by five months, removing two milestones outside the grant scope, and altering the project completion date by five months.

Full council record

Decision

That the Director of Delivery and Operations, in consultation with Directors, approves the changes to Bristol Energy Network’s Sustainable Innovative Financial Foundations for Turbines project, that:

  1. the proposed changes to the milestones and dates which will allow the project to meet deliverables and complete the project by the end of January 2027. As set out in the table below.

·        To change two milestones by 5 months, from July 26 to December 26

·        To remove two milestones that fall outside of the scope of the grant scope

·        To change the completion date by 5 months from August 26 to January 27


Milestone changes

Milestone

Last Reported

Proposed

Planning permission applications submitted

July 26

December 26

Funding in Principle and Due Diligence commencement

July 26

Remove milestone – Falls outside of grant scope.

Financial Close on wind turbine projects

July 26

Remove milestone – Falls outside of grant scope.

Stage 5 Completed

July 26

December 26

Evaluation and project close out

August 26

January 27

Project Completion

08/26

01/27

Supporting Documents

136 SUSTAINABLE INNOVATIVE FINANCIAL FOUNDATIONS FOR TURBINES CHANGE REQUEST.pdf

Details

OutcomeRecommendations Approved
Decision date24 Aug 2026