Community Transport (Transport Levy): To continue to fund Community Transport to at least April 2027
October 12, 2026 Director of Bus Operations (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Director of Bus Operations approved an increase in Transport Levy grants for Community Transport schemes totalling £432,149.35, and an increase in the Concessionary Reimbursement budget by £259,791.81, both to cover the final six months of the 2026/2027 financial year. The decision also approved a delay of the "Delivery of Community Transport" milestone to 31 March 2027 and allocated £17,296.50 as contingency.
Full council record
Decision
That the Director of Bus Operations:
- Approves increase in Transport Levy grants for Community Transport schemes listed below, totalling £432,149.35, to cover operations for the final 6 months of the 2026/2027 financial year. Values are listed in the table below.
- Approves delay of “Delivery of Community Transport” milestone from 30 Sep 2026 to 31 March 2027 for all such grants.
- Approves increase in Concessionary Reimbursement budget by £259,791.81 to cover the final 6 months of the 2026/2027 financial year.
- Approves £17,296.50 to be spent as contingency on Community Transport.
Table 1. Existing Community Transport schemes with 6 months of costs
Community Transport Operator
Anticipated 6-month cost
Oct 2026 - Mar 2027
B&NES Council (Bath Dial A Ride)
£24,121.78
Bath Community Transport
£30,600.00
Green Community Transport
£58,634.04
Hartcliffe & Withywood Community Transport
£95,586.75
Hawkesbury Volunteer Transport Group
£612.00
Keynsham & District Dial A Ride
£54,060.00
Kingswood Community Transport
£57,149.63
Lawrence Weston Community Transport
£34,476.00
Midsomer Norton Dial A Ride
£66,372.55
St Phillips & St James Church
£2,900.80
Swan Advice Network
£7,635.80
Grant Total
£432,149.35
Concessionary Fares (estimate)
£259,791.81
Remaining Contingency
£17,296.50
Overall Total
£709,237.66
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 12 Oct 2026 |