Brabazon (North Filton) Operating Cost Protection Deed (OPEX) - Additional Train Per Hour
November 10, 2026 Director of Transport Programmes (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Director of Transport Programmes, David Jarman, approved the West of England Combined Authority (MCA) entering into the Brabazon (North Filton) Operating Cost Protection Deed (OpEx) with Great Western Railway (GWR) on 10/11/2026. This authorises the MCA to procure and revenue fund an additional train set for an interim passenger service ahead of the Henbury turnback facility's completion, with an estimated total value of £1,091,762.15. The decision was deemed urgent and exempt from the normal call-in period due to risks of serious prejudice to the interests of the Authority and its residents if the decision was deferred.
Full council record
Decision
That:
1) Approval is granted for the West of England Combined Authority (MCA) to enter into the Brabazon (North Filton) Operating Cost Protection Deed (OpEx) with Great Western Railway (GWR). This authorises MCA to procure and revenue fund the operation of an additional train set required to deliver the interim 1 train per hour (1tph) passenger service ahead of completion of the Henbury turnback facility.
2) The estimated total value of this agreement is £1,091,762.15 including indexation. This is based on the contract being open for 2 years (November 2026 to November 2028), as per current programme, and terminated upon completion of the Henbury Turnback, which removes the requirement for an additional train unit.
Supporting Documents
Details
| Reference | Call-ins0 |
| Outcome | Recommendations Approved |
| Decision date | 10 Nov 2026 |