Variation to MW2 Phase 2 - NF - Implementation Agreement, Secondary Means of Escape (SME)

November 13, 2026 Chief Executive, West of England Combined Authority (Officer) Key decision In call-in window View on council website

This summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.

Summary

The Chief Executive of the West of England Combined Authority decided to approve a contract variation. This variation awards Network Rail an additional £3,664,909 for the MW2 Phase 2 – NF – Implementation Agreement, bringing the new total contract value to £27,881,622, as of 13/11/2026.

Full council record

Decision

That:

Network Rail are awarded a contract variation to the original MW2 Phase 2 – NF – Implementation Agreement

The total original contracted price is £24,216,713

The variation is for £3,664,909


New Contract Value is £27,881,622

Supporting Documents

Variation to MW2 Phase 2 NF Implementation Agreement Secondary Means of Escape SME.pdf

Details

ReferenceCall-ins0
OutcomeRecommendations Approved (subject to call-in)
Decision date13 Nov 2026
Subject to call-inYes