Award of contract for the replacement of modular teaching accommodation at Slinfold CE Primary School - OKD10(25/26)
September 22, 2025 Assistant Director (Property and Assets) (Andrew Edwards) (Officer) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
...to award the construction contract for £1,290,444 to E W Beard Ltd for a two-class extension at Slinfold CE Primary School, replacing the existing modular teaching accommodation.
Full council record
Purpose
Slinfold CE Primary School is a 140
place Primary School for 4–11-year-olds incorporating five
classrooms and a pre-school on site. Two of the five classrooms are
in 30-year-old modular classrooms, which have significant
suitability and condition issues due to the age of the buildings
and are nearing the end of their life.
In December 2021 approval
(decision
LS12 (21/22) refers) was given for the allocation of funding to
replace the modular classrooms with a two-class extension and
authority was delegated to the Assistant Director (Property and
Assets) to procure a contractor to complete the works. Unforeseen delays to the project and inflationary
pressures meant that in May 2025, the Cabinet Member for Children,
Young People and Learning approved an increase in funding (decision
CYPL01(25/26) refers) for delivery of the project.
A procurement exercise has been
undertaken to appoint a contractor, and authority is now sought for
a decision to award the contract to enable the delivery of the
two-class extension.
Decision
The Assistant Director (Property and Assets)
has approved the award of the construction contract to E W Beard
Ltd for the delivery of the 2-class extension to replace the
modular teaching accommodation at Slinfold CE Primary School for
the value of £1,290,444 (excluding construction contingency
risk). This is affordable within the approved budget of
£1.915m for this project.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 22 Sep 2025 |
| Subject to call-in | Yes |