Made Smarter (Manufacturing)
July 16, 2026 Investment Board (Committee) Key decision Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
The Combined Authority Board approved the Officer Delegation Scheme for Non-Mayoral and Mayoral General Functions on 25 June 2026. The scheme was amended to reflect revised committee names, new legislation, and to clarify its application to officers.
The Assistant Director of People and Transformation authorised the establishment of an interim executive recruitment framework for 12 months, with an option to extend for a further 12 months, on 29 April 2026. This framework is intended to ensure continuity of critical leadership resourcing.
The Executive Director for Transport approved the Active Travel Tranche 4 – Skircoat, Calderdale scheme to proceed to full business case and commence delivery on 2 April 2026. This includes approving further Combined Authority funding of £1,853,617.
The Combined Authority Board approved the revised Corporate Governance Code and Framework on 25 June 2026. This code sets out how the West Yorkshire Combined Authority fulfils the principles of good governance.
Full council record
Purpose
Approval for the scheme to proceed through decision points 2 to 4 (business justification case). This scheme looks to continue delivery of the Made Smarter Yorkshire & Humber programme for West Yorkshire businesses which connects manufacturing industries to digital tools, leadership, and skills to drive growth.
Decision
Made Smarter (Manufacturing)
RESOLVED: – That the Investment Board, subject to conditions, and with reference to 4.65 of the report:
- Approved that the Made Smarter (Manufacturing) scheme proceeds through Decision Point 2 to 4 (Business Justification) and that work commences on Activity 5 (Delivery).
- Approved Combined Authority funding of up to £1,089,362 for the Made Smarter (Manufacturing) scheme, with a total scheme cost of £2,400,000.
- Approved that future approvals for the Made Smarter (Manufacturing) scheme are made in accordance with the assurance pathway, approval route and tolerances set out in the Business Case Summary attached to the report.
Supporting Documents
Details
| Outcome | Recommendations Approved |
| Decision date | 16 Jul 2026 |
| Effective from | 7 Jul 2026 |
| Lead officer | Caroline Farnham-Crossland |