Sheltered Housing Refurbishment and Investment Programme

June 5, 2024 Portfolio Holder for Housing and Welfare (Cabinet member) Key decision Approved View on council website
Full council record

Purpose

Report on the proposed Sheltered housing refurbishment and
investment programme April 2024

Decision

The Portfolio Holder for Housing and Welfare:-
 

(1)     
notes the proposed sheltered housing investment programme as
described in the report, the delivery of which is subject to
further approvals;

(2)     
authorises the commencement of the feasibility stage works on the
Phase 1 schemes identified in the report and to release feasibility
budget requirements – the individual appointment of
consultants will be subject to further approvals;

(3)     
approves the consultation and engagement strategy for the
programme, appended to the report;

(4)     
authorises the statutory public consultation with tenants in the
Phase 1 schemes identified in the report in accordance with the
Housing Act 1985 and all other enabling legislation; and

(5)     
approves that voids are to be held for a 6-month period in each
scheme identified in the Phase 1 programme prior to works starting
and approves a 12-month period of sensitive let prior to this time
to allow as much work as possible to take place.

Details

OutcomeRecommendations Approved
Decision date5 Jun 2024
Subject to call-inYes