OD_26-84: Approval to instruction 150s Architects for the role of principal designer for building regulations at Bevan Road (Marshall Road), Devizes
July 17, 2026 Corporate Director - Place (Officer) Approved View on council websiteThis summary is generated by AI from the council’s published record and supporting documents. Check the full council record and source link before relying on it.
Summary
Corporate Director - Place, acting through the Residential Development Manager, approved instructing One50Studio as Principal Designer for Building Regulations for the Bevan Road development on 17/07/2026. This decision authorises the commitment of funds for the role. The decision includes coordinating designers, reviewing design information for compliance, and preparing statements confirming design compliance.
Full council record
Decision
To instruct One50Studio to act as Principal Designer (PD) for Building Regulations for the proposed development of 32 affordable homes for the site known as Bevan Road,
Devizes and authorise the commitment of funds up to the amount specified
Reasons for the decision
Wiltshire Council’s Residential Development Team are managing the ongoing work Council House Build Programme. The programme is to develop up to 500 homes by 28/29. This site at Bevan Road, off Marshall Road, Devizes is programmed to start on site in the Autumn of 2026.
The Council proposes to build a 100% affordable housing scheme of 32 homes on the land, both contributing towards meeting the ongoing housing need within Devizes, and also meeting the CHBP target of delivery.
Planning permission was granted in December 2025 following the submission of a scheme prepared by Architects One50Studio. The purpose of this decision is to allow One 50 Studio to act as Principal Designer (PD) for Building Regulations interfacing between the client (Wiltshire Council) and the groundworkers (Rigg) in all matters relating to design compliance, building matters and building regulations, covering RIBA stages 4 to 6.
The duties and costs anticipated from One 50 are set out below:
Building Regulations Principal Designer: - Coordinating all designers (civil / structural engineer, MEP, modular manufacturer, etc.) -Reviewing design information for compliance with Parts A–T-Maintaining the Relevant Requirements Tracker and compliance evidence -Ensuring designers provide complete information to support the Building Control Application - Preparing the Principal Designer’s Statement confirming design compliance - (total 7-9 days’ work) July 2026 - September 2026
Building Regulations Principal Designer: - Provides all required compliance information to support the application - Confirms that the design meets building regulations at the point of application - Review any feedback from Building Control that relates to design compliance - (total 1-2 days’ work) September 2026 - October 2026
Assess design variations, substitutions, and modular interface changes for
compliance: - Coordinate updated information from designers and suppliers - Update the PD Statement, Relevant Requirements Tracker, and technical evidence - Respond to Building Control technical queries relating to design - Ensure the Principal Contractor and designers understand compliance-critical elements - NOTE: This is not a site inspection or quality-checking role; it is design-compliance oversight
-(estimate of 6-12 days’ work; fixed fee based on capped 9 days input at [redacted] day rate - 150s reserve the right to agree additional fee if it becomes apparent that more input is required over and above the capped days) - September 2026 - December 2027
Provide updated PD Statements for completion - Ensure as-built information required for Building Control is available (drawings, specs, fire strategy updates, test certificates, commissioning data, etc.) - Review final design information for regulatory compliance before submission for completion certification - Contribute to the Completion Certificate process -(3-5 days work) - December 2027
Total Cost - [redacted] (Allowed for within the capital budget for the project).5. This record of Officer Decision is required to authorise the signing of the Terms of Engagement, by Central Procurement Unit.
The quote received is in line with the sum set out in the Financial Viability
Appraisal for the project.
See attached document for considerations in line with Wiltshire Council’s Constitution.
Alternative options considered
Not to proceed is an option, a Building Regulations Principal Designer must be appointment, otherwise we assume liability for this role, another consultant would have to be found to undertake this role if 150s are not appointed, however the current Architect is the prudent
choice for continuity and competency.